Kacie Rae
We would like to show the Project Managers time as a line item under the summary task. We know that we can have the PM's time calculated as 10% of the overall for reporting, but we would actually like to see a task with start / finish dates (of the entire summary) and then use that line to display the 10%.
Is this possible? Thanks for any thoughts - Kacie
Something like
- Summary Task 6.5 months 1-1-04 6-15-04
PM Time 6.5 days 1-1-04 6-15-04
Item A 3.25 months 1-1-04 3-12-04
Item B 3 months 3-13-04 6-15-04
Is this possible? Thanks for any thoughts - Kacie