Wes Johnson, PMP
I have a project where time worked has to be reported every day. I assign
myself as a resource to two tasks: one is 6 hours over 1 day and the other
is 32 hours over 44 days with my resource loading for the task is set to 10%.
When I view my tasks, the contiguous task of 6 hours let's me enter time day
by day. The task spread over 44 days only allows me to enter % work
complete. What am I not understanding here?
Wes