C
cindy.becken
In a project plan I have assigned Resource A a Task called 'Testing' and
marked the task 60 percent complete. Resource A goes into Web access under
'My Tasks' and see the task 'testing' at 60 percent. Then I go into the
project plan (on my desktop) and update the percent complete to 80, and
republish the plan. If you look at the plan the task 'testing' is now at 80
percent but if Resource A goes to 'My Tasks' it still shows 60 percent, why
is this?
Thanks
marked the task 60 percent complete. Resource A goes into Web access under
'My Tasks' and see the task 'testing' at 60 percent. Then I go into the
project plan (on my desktop) and update the percent complete to 80, and
republish the plan. If you look at the plan the task 'testing' is now at 80
percent but if Resource A goes to 'My Tasks' it still shows 60 percent, why
is this?
Thanks