Hello,
In PWA, in Resource Center, viewing the assignments (button "View
Assignments") of some resources return an empty screen. These resources are
assigned to project.
Furthermore they can submit properly their timesheet.
Also, the "View Availabilty" works fine also.
I was told to make sure it's not a cost resource or budget resource issue.
I don't know exactly how to check this.
Have you other idea.
We are running the Feb 2010 CU patches.