Viewing the bigger picture

L

Lazlo

I’ve been trying to work out how I can get different projects to relate to each other. As I explained previously I have a team of around ten software developers each with different skills in different languages. At different phases of a project’s lifespan I may require the skills of different people. My difficulty is viewing that particular resource’s existing commitments

If I have one developer – Nancy – working on project A from Monday to Thursday, of week one. Then she’s not required on project A until the following Tuesday, until the end of the week. Meanwhile project B needs Nancy’s skills for one day and project C needs her skills for half a day. How can I view from within project B and C when Nancy has free time? And then how would I be able to view the remaining empty half day within that two week period? And ultimately; how would I be able to view when Nancy runs out of work altogether

TI

Laura
 
J

Jan De Messemaeker

Hello,

You have to connect all three projects to a resource pool then you can see
the big picture
Open a new project
save as ... for instance, ABCpool
(but leave open)
open A
Tools, resources, share resources from ABCpool
(even if ABCpool is still empty, don't worry)
open B
Tools, resources, share resources from ABCpool
open C
Tools, resources, share resources from ABCpool
Close and save the lot

Open ABCpool with the third option.
Projectx shows alml the taks of the three projects and its resource view
show total load.
HTH



--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
Lazlo said:
I've been trying to work out how I can get different projects to relate to
each other. As I explained previously I have a team of around ten software
developers each with different skills in different languages. At different
phases of a project's lifespan I may require the skills of different people.
My difficulty is viewing that particular resource's existing commitments.
If I have one developer - Nancy - working on project A from Monday to
Thursday, of week one. Then she's not required on project A until the
following Tuesday, until the end of the week. Meanwhile project B needs
Nancy's skills for one day and project C needs her skills for half a day.
How can I view from within project B and C when Nancy has free time? And
then how would I be able to view the remaining empty half day within that
two week period? And ultimately; how would I be able to view when Nancy runs
out of work altogether?
 