M
M. Schmidt
Hello,
I’ve been digging around in Project 2007 Professonal and can’t figure out
how to get the information I’m looking for. In my workplan, all my resources
are setup using the Standard calendar which has holidays and the weeks of
Christmas and New Years blocked out as Non-Working time because we wanted to
acccount for the fact that so many people take vacations during that time
when we were working out the project schedule earlier in the year and didn't
know yet exactly who would be taking vacation time and which days they would
be out. Now that the holiday season is closer and people are firming up their
vacation plans, I want to change the weeks of Christmas and New Year’s back
to regular working time on my Standard calendar except for the holidays
themselves and just manage vacation days at a resource level. I have
vacations entered for some of my resources, but I’m not sure if I have
EVERYONE’S vacation schedule in there yet or not.
I’m trying to figure out if there’s a way I can see a View, or a Report, or
get an Export that shows all the Working Time Exceptions I’ve listed for each
resource. Is there a way I could get that information so I can verify that I
have everyone’s vacation scheduled entered without having to open up each
individual resource record? Can I even get this information without having to
create a custom SQL query against the database itself?
Thanks in advance,
Misty
I’ve been digging around in Project 2007 Professonal and can’t figure out
how to get the information I’m looking for. In my workplan, all my resources
are setup using the Standard calendar which has holidays and the weeks of
Christmas and New Years blocked out as Non-Working time because we wanted to
acccount for the fact that so many people take vacations during that time
when we were working out the project schedule earlier in the year and didn't
know yet exactly who would be taking vacation time and which days they would
be out. Now that the holiday season is closer and people are firming up their
vacation plans, I want to change the weeks of Christmas and New Year’s back
to regular working time on my Standard calendar except for the holidays
themselves and just manage vacation days at a resource level. I have
vacations entered for some of my resources, but I’m not sure if I have
EVERYONE’S vacation schedule in there yet or not.
I’m trying to figure out if there’s a way I can see a View, or a Report, or
get an Export that shows all the Working Time Exceptions I’ve listed for each
resource. Is there a way I could get that information so I can verify that I
have everyone’s vacation scheduled entered without having to open up each
individual resource record? Can I even get this information without having to
create a custom SQL query against the database itself?
Thanks in advance,
Misty