HI Gurus,

I customized the Global Enterprise adding a new view (Table+Filter). After
saving this view and opening Project Pro I am now receiving two dialog box,
one stating "There is a view named &Gantt Chart in this project which cannot
be overwritten. Press OK to rename it or press cancel to cancel opening the
project", and the second one "There is a table named &Entry which cannot be
overwritten. Press OK to rename it or press cancel to cancel opening the
project". I renamed both objects and went to the Organizer; obviously there
is the Gantt Chart view, The Entry table and the recently renamed objects. I
can't delete the new objects.

I don't want to rename any objects and just want to restore the
functionality as it was before modifying the Global Enterprise

Thanks in advance

Mauricio
 
M

Mauricio Iannini, PMP, MCITP

Dale,

Thanks as always. My two cents on the topic: the Gantt Chart cannot be the
selected view when deleting both the view or the Entry table.

Mauricio
 
D

Dale Howard [MVP]

Maruicio --

Correct. I recommend that you leave the Enterprise Gantt Chart as the
current View in the Enterprise Global. And you are more than welcome for
the help, my friend! :)
 