Views in Project Center

H

Hari

Hi,
We are using MS Project Professional 2007 and project server 2007. In PWA
views, how will I be able to see the Datum Exposure and Status view?
This view doesnt show up in the list? Do I need to create any custom fields
or views to be able to see this view?
Thank you in advance!
 
J

Jonathan Sofer

I am assuming this is a Project Center view available in the Manage Views
section of Server Settings? Try adding the view to all the security
categories or at least one that you know you have access to. This can be
done at the bottom of the edit view page.
 
H

Hari

Hi Jonathan,
I went to Manage views, but for some reasons, I dont see that specific view.
Do I need to create a new view and add all security categories? Is that what
you meant by adding the view to all security categories?

I see several View names for instance : Assignments Cost, Assignments
Detail, Resource Cost etc..etc...
Thank you in advance!
 
H

Hari

It appears that I dont have the custome fields defined for this view.
Can anyone help me in creating
MSP Field : Enterprise Project Text1
Custom Field: Project Budget
Order : 2
Width 100
Autosize : Yes
Table :
Gantt Scheme: Gantt chart
Grouping Scheme : TImesheet
 
C

Chak

Hi Hari,

Steps to create PWA view:

PWA home -> Server Settings -> Click on "Manage Views" under Look and
Feel

Click on "New View"

Choose View Type from dropdown

Give the name for the view

Add required columns from Available fields

Choose security categories from “Available categories”

Click Save


Thanks
Chak
http://www.epmcentral.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top