Is there a way to show a project in weeks or months instead of days? I need to get six months on a report and with it showing each individual day I can not fit the who project on one sheet

Thanks
 
J

John

Debbie,
For reports that show timescale data, go to View/Reports and select the
applicable report category (e.g. Workload). Then select the individual
report and hit "edit". Change the column heading on the Crosstab to
weeks or months as desired.

Hope this helps.
John
 