O
Office_dummy
Hi there
I have relatively basic Visio skills, and want to know whether it is
possible to have a check box function in the process which allows to show if
a task is either:
1. not started
2. in progress
3. completed
the simpliest way was to get the staff to colour the box a different colour
as tasks were moved along but i would a way for them to just hit a check box
of one of the above and have the shape in which that task sits in to be a
different colour.
Thanks
I have relatively basic Visio skills, and want to know whether it is
possible to have a check box function in the process which allows to show if
a task is either:
1. not started
2. in progress
3. completed
the simpliest way was to get the staff to colour the box a different colour
as tasks were moved along but i would a way for them to just hit a check box
of one of the above and have the shape in which that task sits in to be a
different colour.
Thanks