P
plf100
Is there any logic to the order in which Project exports the WBS into Visio?
Initially I thought it might have been ordered by WBS code but no, then I
thought it might be to do with start date of tasks but no. I did a little
experiment with a project with only 4 simple tasks and used the wizard 3
times consecutively; on each Visio drawing the tasks were all ordered
differently!
Am I missing something fundamental?
Many thanks.
Initially I thought it might have been ordered by WBS code but no, then I
thought it might be to do with start date of tasks but no. I did a little
experiment with a project with only 4 simple tasks and used the wizard 3
times consecutively; on each Visio drawing the tasks were all ordered
differently!
Am I missing something fundamental?
Many thanks.