Alan Dods
Hello
I am trying to import a project saved in Project 2000 (mpp format)
into Visio 2002 using the Gantt chart import wizard.
It contains a large number of tasks of 2 hour duration.
Visio is showing these tasks as milestones of 0 duration. Does anyone
know how I can fix this or work around?
Thanks
Alan
I am trying to import a project saved in Project 2000 (mpp format)
into Visio 2002 using the Gantt chart import wizard.
It contains a large number of tasks of 2 hour duration.
Visio is showing these tasks as milestones of 0 duration. Does anyone
know how I can fix this or work around?
Thanks
Alan