H
Hadi
Experts, from reading some of the existing postings here it seems that Visual
reports in 2007 do not work as well when generated from a master schedule. I
have a master schedule that has its own wbs and tasks, but also has two
inserted projects inside. the tasks within the master are resource loaded
using resource from the enterprise pool. when try to generate an assignment
time phased report to excel, the work hours are multiplied by 8. any ideas?
reports in 2007 do not work as well when generated from a master schedule. I
have a master schedule that has its own wbs and tasks, but also has two
inserted projects inside. the tasks within the master are resource loaded
using resource from the enterprise pool. when try to generate an assignment
time phased report to excel, the work hours are multiplied by 8. any ideas?