Visual Report - not computing Work Availability

S

ST

Hi,

The 'Work Availability' data that I'm getting via the Resource Work
Availability Visual Report is only showing values for one day (Week 38, Day
24) for a the project file that is saved on Project Server 2007. The report
runs fine when I use it on a similar project that is saved locally on the PC.

I thought I'ld check the Resource Availability view in the PWA Resource
Center to see if the capacity data was being displayed correctly there.
Indeed it is.

So, what could be preventing Visual Reports from displaying the 'Work
Availability' data accross all my time periods for my enterprise project?

/SpiroT/
 
M

MSPLearner

Hello SpiroT,

Like you, I also want to create a availability report (timephased) - were
you able to figure out and would be willing to share?

MSPLearner
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top