J
jackie
Hello
I would like to find out what is the most efficient way to check the status
of the predecessors of any tasks in the plan
I have a plan with a large number of tasks and for instance task 540, has 10
predecessors each at different stages of completion scattered throughout the
plan. Currently if I want to know how each predecessor is progressing I need
to locate the predecessor manually, and I would be grateful for some advice
on how to do this more efficiently
Many thanks
J
I would like to find out what is the most efficient way to check the status
of the predecessors of any tasks in the plan
I have a plan with a large number of tasks and for instance task 540, has 10
predecessors each at different stages of completion scattered throughout the
plan. Currently if I want to know how each predecessor is progressing I need
to locate the predecessor manually, and I would be grateful for some advice
on how to do this more efficiently
Many thanks
J