WBS field in Timesheet View

S

Scott Robertson

Is there anyway to get the WBS field working in the timesheet view?

I have added the field to the PWA view, but it does not return any
information.

Thanks in advance.
 
D

Dale Howard [MVP]

Scott --

Your project managers need to the following in EVERY project that they
manage:

1. Open a project
2. Click Tools - Customize - Published Fields
3. Select the WBS field from the list on the left and copy it to the list
on the right
4. Click the OK button
5. Click Collaborate - Publish - Republish Assignments and click OK

Doing so will "push" the data from the WBS field to the WBS column in each
user's timesheet in PWA. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top