In MS Project 2000 (SP-1), moving a task from one location
to another in the plan does not dynamically change the WBS
ID, and it should. Has anyone else notice this?
 
J

Jan De Messemaeker

Hi Rob,

What was called WBS in P98 is called Outline Number in P2000, and that one
always changes allright.
A customized WBS doesn't automatically; you have to activate Project, WBS,
Renumber.
HTH
 
G

Guest

Project/WBS/Renumber was greyed out for some reason. But
I created a new column in the "Outline Number" format
which should work.

Thanks!
 