I added the WBS column to Timesheet view in Manage views (PWA Admin), it
shows up in Tasks but contains no data. What else should I do?

kattial
 
G

Gérard Ducouret

Kattila,

Open each project, then Publish all information
Hope this helps,

Gérard Ducouret
 
K

kattila

Gérard,

No it did not. Since we are using the system for time tracking as well,
plans are update and published frequently.

kattila
 
D

Dale Howard [MVP]

Kattila --

You need to republish the assignments for each project by clicking
Collaborate - Publish - Republish Assigments and then clicking OK. This
will "push" the data from the WBS field to each user's timesheet in PWA.
Hope this helps.
 
K

kattila

Guys,

Sorry, I have done what you suggested but no results. WBS shows up in PWA
projects views but not in Timesheet.

kattila
 
D

Dale Howard [MVP]

Kattila --

Oops! I skipped a step and I apologize. Each project manager needs to do
this for EVERY project he/she manages:

1. Open a project
2. Click Tools - Customize - Published Fields
3. Add the WBS field to the list on the right
4. Click OK
5. Click Collaborate - Publish - Republish Assignments and click OK
6. Repeat steps #1-5 for every project

Hope this helps.
 
K

kattila

Thanks

Dale Howard said:
Kattila --

Oops! I skipped a step and I apologize. Each project manager needs to do
this for EVERY project he/she manages:

1. Open a project
2. Click Tools - Customize - Published Fields
3. Add the WBS field to the list on the right
4. Click OK
5. Click Collaborate - Publish - Republish Assignments and click OK
6. Repeat steps #1-5 for every project

Hope this helps.
 