When you link a task in one schedule with a task in another schedule,
that external task shows in the orignial schedule grayed out. If you
show the WBS field in the view, the external task's WBS number comes
with it. Even though the external task's WBS number shows in the WBS
column, the original schedule counts that line when figuring the WBS
for the schedule. For example, if I link line 3 to an external task,
the WBS will look like this:
1
1.1
1.2
6.4.11
1.4
Line 4 is the external task. But, as you can see, WBS number 1.3 is
missing because that is where the external tasks is. Is there a way to
ignore the external tasks when figuring the WBS? Simply not showing
the external task will not renumber the WBS.
Thx.
that external task shows in the orignial schedule grayed out. If you
show the WBS field in the view, the external task's WBS number comes
with it. Even though the external task's WBS number shows in the WBS
column, the original schedule counts that line when figuring the WBS
for the schedule. For example, if I link line 3 to an external task,
the WBS will look like this:
1
1.1
1.2
6.4.11
1.4
Line 4 is the external task. But, as you can see, WBS number 1.3 is
missing because that is where the external tasks is. Is there a way to
ignore the external tasks when figuring the WBS? Simply not showing
the external task will not renumber the WBS.
Thx.