B
Brian
Hi All,
I have read previous threads that have discussed this, but do not seem to
conclude with a solution. What I am after is the capability to look at a
summary level view of resources using a WBS structure. For example, I have
WBS below,
WBS 1 - Design Widget
WBS 1.1 Analyze Requirements (resourses Tom 20 hrs, Dick 40 hrs, and Harry
100 hrs)
WBS 1.2 Draft Design
WBS 1.2.1 Invent Wheel (resources Tom 10 hrs, Dick 20 hrs, Harry 50 hrs,
$10000 Material)
WBS 1.2.2 Invent Wagon (resources Tom 10 hrs, Dick 20 hrs, Harry 50 hrs,
$10000 Material)
WBS 2 - Test Widget
WBS 2.1 Lab/Bench Abuse Test (resourses Tom 20 hrs, Dick 40 hrs, Harry 100
hrs, $10000 Material)
WBS 2.2 Beach Test (resources Tom 20 hrs, Dick 40 hrs, Harry 100 hrs, $20000
Material, $10000 Travel)
I would like to see a task usage summary,
WBS 1 - Design Widget
Tom 40 hrs
Dick 80 hrs
Harry 200 hrs
Material $20000
WBS 2 - Test Widget
Tom 40 hrs
Dick 80 hrs
Harry 200 hrs
Material $30000
Travel $10000
I was able to kind of get this with MP with various reports or group views,
but both do not total up at the top summary level. This seems to be a pretty
basic item for a schedule/resource management package.
Thanks,
Brian
I have read previous threads that have discussed this, but do not seem to
conclude with a solution. What I am after is the capability to look at a
summary level view of resources using a WBS structure. For example, I have
WBS below,
WBS 1 - Design Widget
WBS 1.1 Analyze Requirements (resourses Tom 20 hrs, Dick 40 hrs, and Harry
100 hrs)
WBS 1.2 Draft Design
WBS 1.2.1 Invent Wheel (resources Tom 10 hrs, Dick 20 hrs, Harry 50 hrs,
$10000 Material)
WBS 1.2.2 Invent Wagon (resources Tom 10 hrs, Dick 20 hrs, Harry 50 hrs,
$10000 Material)
WBS 2 - Test Widget
WBS 2.1 Lab/Bench Abuse Test (resourses Tom 20 hrs, Dick 40 hrs, Harry 100
hrs, $10000 Material)
WBS 2.2 Beach Test (resources Tom 20 hrs, Dick 40 hrs, Harry 100 hrs, $20000
Material, $10000 Travel)
I would like to see a task usage summary,
WBS 1 - Design Widget
Tom 40 hrs
Dick 80 hrs
Harry 200 hrs
Material $20000
WBS 2 - Test Widget
Tom 40 hrs
Dick 80 hrs
Harry 200 hrs
Material $30000
Travel $10000
I was able to kind of get this with MP with various reports or group views,
but both do not total up at the top summary level. This seems to be a pretty
basic item for a schedule/resource management package.
Thanks,
Brian