WBS

S

shlomimh

Hello, I'm working with Project Server 2003, and I'm trying to find the table
that contains the WBS- in order to get the task hierarchy (table
name:MSP_TASKS field name:TASK_WBS).
The problem is that some tasks appear not to have a WBS.
Is there another way to get the task hierarchy?
Shlomi Mor-Hayim
 
J

John

shlomimh said:
Hello, I'm working with Project Server 2003, and I'm trying to find the table
that contains the WBS- in order to get the task hierarchy (table
name:MSP_TASKS field name:TASK_WBS).
The problem is that some tasks appear not to have a WBS.
Is there another way to get the task hierarchy?
Shlomi Mor-Hayim

shlomimh,
Project automatically adds an entry in the WBS field when tasks are
created. That entry can be deleted or changed manually by the user after
the fact. However, since this is a question for Project Server, I
suggest you post to our sister newsgroup,
microsoft.public.project.server. This newsgroup is dedicated to the
stand alone versions of Project.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top