When going to admin -> customize -> Gantt Chart Formats, the title says
"Specify the bar styles and timescale for Gantt charts". However, I can not
find anything on how to change the default timescale. Our charts are
"zoomed" in too far, and we'd like to default to a wider time phase (ie,
quarterly instead of weekly). Is there a way to do this given the fact that
the UI doesn't allow it? Does Server 2003 fix this?

Thanks for any help/info!
 
D

Dale Howard [MVP]

Mark --

The title is erroneous. You cannot change the timescale in PWA views. You
can't change it in Project Server 2003 either. Sorry.
 
G

Gary L. Chefetz [MVP]

Mark:

You can only change the timescale when you're using the view, not while
building it.
 
M

Mark

We actually found how to modify the InitZoomControls function to set a new
default zoom for the Gantt chart. Thanks for the replies, though!
 