M
MaryB
I am just beginning to set up projects in MS Server 2002. There will be
multiple projects posted on Web Access, with many departments accessing them.
I would like to set up projects so that, when resources select a project,
the task sheet shows only summary tasks, enabling them to bypass sifting
through hundreds of subtasks. Is it possible to set up projects so that
they show only outline level 1, but still allow resources to roll down to
view all subtasks?
multiple projects posted on Web Access, with many departments accessing them.
I would like to set up projects so that, when resources select a project,
the task sheet shows only summary tasks, enabling them to bypass sifting
through hundreds of subtasks. Is it possible to set up projects so that
they show only outline level 1, but still allow resources to roll down to
view all subtasks?