S
Stephan Steiner
Hi
Our Project => SAP actuals export fell flat on its nose today because a few
Task EFs were missing. Upon further investigation, I found that I have a
handful of entries in MSP_WEB_WORK whose corresponding entry in the
MSP_WEB_ASSIGNMENTS table lacks the ASSN_ID, TASK_ID and TASK_UID, and hence
no task EFs can be found.
I started checking the fields of the MSP_WEB_ASSIGNMENTS table and found
that all have the WASSN_IS_CONFIRMED field set to 1, many are self-assigned
and not yet approved (WASSN_CREATED_BY_RES = 2), all but one need to be
updated (WASSN_SEND_UPDATE_NEEDED = 1) and all but two have pending actuals
(WASSN_ACTUALS_PENDING = 1)
Since I'm not the project pro, I'm wondering about a few things regarding
the assignments I'm seeing:
Is it possible to have assignments in properly submitted and approved (be
they user created or created by the project manager) state, with ASSN_ID,
TASK_ID or TASK_UID not set? I thought Project always had the following
hierarchy: Project - Task (0 - n) - Assignment (0 - n). It is not yet time
for these actuals to be exported so I suppose all the actuals will be
submitted and approved by the time the export is supposed to run, but this
just got me somewhat worried. It appears for past weeks, everything is in
order, but I'd rather not rely on having been lucky then and get to the
bottom of this.
Can I count on the entries in the MSP_TASKS and MSP_ASSIGNMENTS tables being
created once the actuals have been submitted and approved?
Regards
Stephan
Our Project => SAP actuals export fell flat on its nose today because a few
Task EFs were missing. Upon further investigation, I found that I have a
handful of entries in MSP_WEB_WORK whose corresponding entry in the
MSP_WEB_ASSIGNMENTS table lacks the ASSN_ID, TASK_ID and TASK_UID, and hence
no task EFs can be found.
I started checking the fields of the MSP_WEB_ASSIGNMENTS table and found
that all have the WASSN_IS_CONFIRMED field set to 1, many are self-assigned
and not yet approved (WASSN_CREATED_BY_RES = 2), all but one need to be
updated (WASSN_SEND_UPDATE_NEEDED = 1) and all but two have pending actuals
(WASSN_ACTUALS_PENDING = 1)
Since I'm not the project pro, I'm wondering about a few things regarding
the assignments I'm seeing:
Is it possible to have assignments in properly submitted and approved (be
they user created or created by the project manager) state, with ASSN_ID,
TASK_ID or TASK_UID not set? I thought Project always had the following
hierarchy: Project - Task (0 - n) - Assignment (0 - n). It is not yet time
for these actuals to be exported so I suppose all the actuals will be
submitted and approved by the time the export is supposed to run, but this
just got me somewhat worried. It appears for past weeks, everything is in
order, but I'd rather not rely on having been lucky then and get to the
bottom of this.
Can I count on the entries in the MSP_TASKS and MSP_ASSIGNMENTS tables being
created once the actuals have been submitted and approved?
Regards
Stephan