Week number US start at first Sunday of the new year.
In Europe the first week is the week of 01 January.
In US 16April09 is in week 15, but for Europe this is week 16.
 
G

Gérard Ducouret

Hello,

In Europe as elsewhere, the ISO 8601 standard says that the week #1 is that
which contains the first Thursday.

Gérard Ducouret
 
G

Gérard Ducouret

Hi Jan,

If I remember well, Project complies with the ISO week numbering since 2003
version. But I'm not sure...

Gérard
 
J

Jan De Messemaeker

Hi,

Recently, on the Dutch NG I had a poster who asked for a formula to
calculate the ISO number; he claimed that Project hadn't. Now I haven't
chcked it in detail..

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top