R
Robert
Hello,
I'm using Project Server 2007 with SP1 + IU
I built a pivot table view in the OLAP Cube, with a timescale of 22 weeks
from 1st of January 2009.
But the week numbers are quite disorganized. I can accept to understand that
a week can be spread over 2 months, but the week 9 appears 2 times,
separated by 5 other weeks. (see below) I'm afraid that many users will get
disorientated.
Is it possible to avoid this stupid numbering ? Thanks for your help
Week1
Week2
Week3
Week4
Week5
Week5
Week6
Week7
Week8
Week9
Week10
Week11
Week12
Week13
Week14
Week9
Week14
Week15
Week16
Week17
Week18
Week18
Week19
Week20
Week21
Week22
I'm using Project Server 2007 with SP1 + IU
I built a pivot table view in the OLAP Cube, with a timescale of 22 weeks
from 1st of January 2009.
But the week numbers are quite disorganized. I can accept to understand that
a week can be spread over 2 months, but the week 9 appears 2 times,
separated by 5 other weeks. (see below) I'm afraid that many users will get
disorientated.
Is it possible to avoid this stupid numbering ? Thanks for your help
Week1
Week2
Week3
Week4
Week5
Week5
Week6
Week7
Week8
Week9
Week10
Week11
Week12
Week13
Week14
Week9
Week14
Week15
Week16
Week17
Week18
Week18
Week19
Week20
Week21
Week22