Week Start in Project Web Access

D

dave

Currently in Project Web access in the timesheet view it does not show Sat as
the start of the week.
I believe i changed this option on the admin menu but this change is not
reflected in the timesheet view.
How do i modify project to show sat as the start of the week?

thank you
dave
 
D

Dale Howard [MVP]

Dave --

Are you certain you set Saturday as the start of the week in Project Server?
Perform these steps to confirm:

1. Log into PWA with administrator permissions
2. Click the Admin menu
3. Click the Customize Project Web Access link
4. Set the Week Starts On value to Saturday
5. Click the Save Changes button

Let us know if this does not solve the problem.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
D

dave

Dale, correct I followed your instructions below but still when i view
timesheets through PWA I see Sunday as the start of the week. I need to see
Saturday on the left in the timesheet view.

I hope you know what may be going on.
thx again
dave
 
D

Dale Howard [MVP]

Dave --

I'm not sure what is causing your problem. All I know is that the steps
work for my Project Server instances. Sorry.
 
D

dave

Thank you for the quick response Dale.

Just to be clear, you are saying that after you follow the steps documented
in this thread that when you view the timesheet through Project Web Access
Saturday appears on the left in the timesheet view?
 