C
cayce
I am in Sales and I create a "preliminary" Microsoft schedule for my
proposal. This schedule is intended to start / end dates and task duration
along with required predecessor/successor links.
Our company just recently converted to Microsoft Project 2007.
For installation of the work, I need to show weekend installation only, for
nine consecutive weekends. I created a new calendar called "Weekend Work" and
linked the pertinent tasks to this new schedule. My first installation is for
3 days with a start of Saturday and end date of Tuesday. It should have an
end date of Monday. My remaining installation tasks have a duration of 2 days
with a start of Saturday and an end date of Monday. It should have an end
date of Sunday.
I tried to force the dates, but it will not reflect the forced change.
What am I missing?
proposal. This schedule is intended to start / end dates and task duration
along with required predecessor/successor links.
Our company just recently converted to Microsoft Project 2007.
For installation of the work, I need to show weekend installation only, for
nine consecutive weekends. I created a new calendar called "Weekend Work" and
linked the pertinent tasks to this new schedule. My first installation is for
3 days with a start of Saturday and end date of Tuesday. It should have an
end date of Monday. My remaining installation tasks have a duration of 2 days
with a start of Saturday and an end date of Monday. It should have an end
date of Sunday.
I tried to force the dates, but it will not reflect the forced change.
What am I missing?