Hi,
A workaround is to have them as non-working days in the project calendar,
but to base all resoruce calendars on a 7/7 calendar, thus tehy will work
weekends but the view knows them as non-working
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
Lac said:
Is there anyway to have weekends grey shaded in the calendar view, yet
still have them be working days? So far, I've only found either gray and
non-working or white and working.