D
Derrick Rand
I read your original post below with regards to scheduling over the weekends. The task bars appear that work occurs over the weekend even though the weekends are scheduled as nonworking time. A little misleading but thanks for the answer there.
I do have one additional issue, though. When I split a task over a weekend period, say if I split a task on Friday and expect for the work to start back up on Monday I can only start the task back up on a Tuesday when dragging the taskbar backwards. What gives?
Derrick Rand
Subject: Re: Project Calendar 5/19/2004 7:40 AM PST
By: Gérard Ducouret In: microsoft.public.project
Was this post helpful to you?
Hello Brian,
The tasks bars cross the weed-end but they don't use it. Count all the
working days. MS Project durations are specified in working days by default.
You can set Ms Project to dsiplay the non-working time in front of the tasks
bars :
Format / Timescale... / Non working time / Draw : In front off...
Hope this helps,
Gérard Ducouret [Project MVP]
PragmaSoft ® - Paris
weekends days are included in the task as working days. Any suggestions how
I can keep my weekends as non-working time?
I do have one additional issue, though. When I split a task over a weekend period, say if I split a task on Friday and expect for the work to start back up on Monday I can only start the task back up on a Tuesday when dragging the taskbar backwards. What gives?
Derrick Rand
Subject: Re: Project Calendar 5/19/2004 7:40 AM PST
By: Gérard Ducouret In: microsoft.public.project
Was this post helpful to you?
Hello Brian,
The tasks bars cross the weed-end but they don't use it. Count all the
working days. MS Project durations are specified in working days by default.
You can set Ms Project to dsiplay the non-working time in front of the tasks
bars :
Format / Timescale... / Non working time / Draw : In front off...
Hope this helps,
Gérard Ducouret [Project MVP]
PragmaSoft ® - Paris
However, when I have tasks cross a weekend (i.e. a 10 day task), theBrian said:I have the working days in my calendar set to Monday through Friday.
weekends days are included in the task as working days. Any suggestions how
I can keep my weekends as non-working time?