Project Standard 2003, No project server...
I have a multi-project schedule, with one resource pool...
I am trying to schedule weekends for 3 particular resources inside of one
project. I am going to Tools | Change Working Time, and choosing the proper
resource(s) from the 'For' pulldown. I am then setting the weekend days to
working days by selecting them, choosing 'non-default working time' entering
the weekend working hours accordingly.
The problem is, when i save, close, and reopen the schedule, the weekends I
set to be working times reset back to non working times.
What am I doing wrong?
TIA,
Lance
Project Standard 2003, No project server...
I have a multi-project schedule, with one resource pool...
I am trying to schedule weekends for 3 particular resources inside of one
project. I am going to Tools | Change Working Time, and choosing the proper
resource(s) from the 'For' pulldown. I am then setting the weekend days to
working days by selecting them, choosing 'non-default working time' entering
the weekend working hours accordingly.
The problem is, when i save, close, and reopen the schedule, the weekends I
set to be working times reset back to non working times.
What am I doing wrong?
TIA,
Lance