D
Daniel Keen
I'm trying to create a report for one of our execs that looks something like
this:
Resource/Task Weekly Total Month to Date Total
Resource #1
Task #1 Weekly Task Total Month to Date Total
Task #2 Weekly Task Total Month to Date Total
Resc. Wkly Total Resc. MTD Total
Resource #2
Task #1 Weekly Task Total Month to Date Total
Task #2 Weekly Task Total Month to Date Total
Resc. Wkly Total Resc. MTD Total
Grand Totals
I can get the Weekly totals by modifying the Who Does What When report, and
the MTD in a view in Portfolio Analyzer, but I can't seen to get both of
them on the same report. Portfolio Analyzer would be ideal, but the time
values jump from daily to monthly. Is there a way to do this either with
reports in Project or PWA without having to use an external reporting system
and/or data warehouse?
this:
Resource/Task Weekly Total Month to Date Total
Resource #1
Task #1 Weekly Task Total Month to Date Total
Task #2 Weekly Task Total Month to Date Total
Resc. Wkly Total Resc. MTD Total
Resource #2
Task #1 Weekly Task Total Month to Date Total
Task #2 Weekly Task Total Month to Date Total
Resc. Wkly Total Resc. MTD Total
Grand Totals
I can get the Weekly totals by modifying the Who Does What When report, and
the MTD in a view in Portfolio Analyzer, but I can't seen to get both of
them on the same report. Portfolio Analyzer would be ideal, but the time
values jump from daily to monthly. Is there a way to do this either with
reports in Project or PWA without having to use an external reporting system
and/or data warehouse?