M
Michael David Pedersen
Hello all,
I am currently using Project 2007 Pro for the long-term (3 years) planning
involving just one resource, namely myself. On the short term, I plan one
week at a time by entering tasks from my Project plan into specific time
slots in an external calendar (the google calendar, to be specific). I then
manually update the task usage in Project accordingly by the end of the week.
My question: is it possible to create weekly plans and assign tasks to the
plan on an hour-by-hour basis _inside_ Project itself? This would save me the
redundancy I am currently experiencing. As far as I can tell, it is only
possible to update tasks by entering task usage per day, which is not quite
what I want. I am new to Project though, so may have overlooked something
obvious...
Any help will be greatly appreciated!
Best regards,
Michael.
I am currently using Project 2007 Pro for the long-term (3 years) planning
involving just one resource, namely myself. On the short term, I plan one
week at a time by entering tasks from my Project plan into specific time
slots in an external calendar (the google calendar, to be specific). I then
manually update the task usage in Project accordingly by the end of the week.
My question: is it possible to create weekly plans and assign tasks to the
plan on an hour-by-hour basis _inside_ Project itself? This would save me the
redundancy I am currently experiencing. As far as I can tell, it is only
possible to update tasks by entering task usage per day, which is not quite
what I want. I am new to Project though, so may have overlooked something
obvious...
Any help will be greatly appreciated!
Best regards,
Michael.