Dear all,
I am facing with this, at the moment strange, issue, I write my timesheet
for a week inserting an amount of hours into a task like:
Monday 2h
Tuesday 4h
Wednesday 5h
Thursaday 0h
Friday 0h
From Project Professional 2007 after the update is approved, if I check the
actual work for the same task into the same period, looking at the week zoom,
values are correct so total actual work is 11h in a week over this task,
looking at the day zoom, unfortunately is not as I sent:
Monday 2h
Tuesday 4h
Wednesday 5h
Thursaday 0h
Friday 0h
but it's reparted in another mood like:
Monday 1,23h
Tuesday 3,5h
Wednesday 6.27h
Thursaday 0h
Friday 0h
what is causing that? Any help about this? I am having some pm complaining
on this because if they check the daily view values are not as sent from
resources.
thank you all
Matteo
I am facing with this, at the moment strange, issue, I write my timesheet
for a week inserting an amount of hours into a task like:
Monday 2h
Tuesday 4h
Wednesday 5h
Thursaday 0h
Friday 0h
From Project Professional 2007 after the update is approved, if I check the
actual work for the same task into the same period, looking at the week zoom,
values are correct so total actual work is 11h in a week over this task,
looking at the day zoom, unfortunately is not as I sent:
Monday 2h
Tuesday 4h
Wednesday 5h
Thursaday 0h
Friday 0h
but it's reparted in another mood like:
Monday 1,23h
Tuesday 3,5h
Wednesday 6.27h
Thursaday 0h
Friday 0h
what is causing that? Any help about this? I am having some pm complaining
on this because if they check the daily view values are not as sent from
resources.
thank you all
Matteo