hello All,
I am a new user of the MS project it would be great if you could help me.
my target is when I report % of completion to the top management not to give all the subtasks the same weight, and the parent row to show real progress as some rows have more progress than the other EX:
I am a new user of the MS project it would be great if you could help me.
my target is when I report % of completion to the top management not to give all the subtasks the same weight, and the parent row to show real progress as some rows have more progress than the other EX:
Hiring |
30 Drivers |
24 Drivers |
4 Trainers |
1 engineer |
1 Deputy |
2 supervisors |
4 Supervisors hence as you see, when I said that 100% is completed for hiring 30 drivers is not the same as saying 100% of hiring 1 engineer. so is there a way to define a weight for each row, or there is another way?" all have the same duration" |