- Joined
- Feb 26, 2018
- Messages
- 1
- Reaction score
- 0
Hello MS Project Guru's,
I am using MS Project 2010 and am trying to create a weight percent complete. I understand the % Complete = (Actual Duration / Duration) * 100. But I need a % complete based on the weight of each task.
So I created a custom field, Weight[Number1], to denote the weight of each task and populated each task with its associated weight. The weight equals 100 for each Child Summery task when it is a 100% complete.
Then created a second custom field, Weight Complete[Number2], and used the formula [% Complete]*[Number1]/100 and set the task and group summary rows to Rollup on the sum.
The third custom field, Weight % Complete[Text3], applies a “%” by using formula [Number2] & " %" and setting the task and group summary rows to Use Formula.
All is working properly for the Child Summery tasks. Where things are breaking down are at the Work Package 1 summery task level. Nothing should go over a 100%, yet the summery task rows are showing numbers like 285% and 385%.
How do I get the Summery Task rows to reflect the percentage complete and not the sum of all the Child Summery tasks under Work Package 1?
Any help would be appreciated. Unfortunately, I am unable to upload my .mpp demo to show you what I'm looking at. Attached is the Excel version.
Robert
I am using MS Project 2010 and am trying to create a weight percent complete. I understand the % Complete = (Actual Duration / Duration) * 100. But I need a % complete based on the weight of each task.
So I created a custom field, Weight[Number1], to denote the weight of each task and populated each task with its associated weight. The weight equals 100 for each Child Summery task when it is a 100% complete.
Then created a second custom field, Weight Complete[Number2], and used the formula [% Complete]*[Number1]/100 and set the task and group summary rows to Rollup on the sum.
The third custom field, Weight % Complete[Text3], applies a “%” by using formula [Number2] & " %" and setting the task and group summary rows to Use Formula.
All is working properly for the Child Summery tasks. Where things are breaking down are at the Work Package 1 summery task level. Nothing should go over a 100%, yet the summery task rows are showing numbers like 285% and 385%.
How do I get the Summery Task rows to reflect the percentage complete and not the sum of all the Child Summery tasks under Work Package 1?
Any help would be appreciated. Unfortunately, I am unable to upload my .mpp demo to show you what I'm looking at. Attached is the Excel version.
Robert