A
Andre
Dear all,
i observe some very strange behaviour of the leveling algorithm of the
MS Project 2003 and would appreciate any ideas on how to fix it.
MS Project Info
------------------------
MS Project Professional 11.0.2003.0816.15
Steps to reproduce a bug
------------------------
1. Create new project
2. Create tasks
Id Task Duration Start End
Predec Ressources
1 T1 5 days Mon 26.12.05 Fri 30.12.05 A
2 T2 5 days Mon 26.12.05 Fri 30.12.05 B
3 T3 5 days Mon 26.12.05 Fri 30.12.05 4SS A
4 T4 5 days Mon 26.12.05 Fri 30.12.05 B
3. Set Prio of Task T1 and T2 to 520, Set Prio of Tasks T3 and T4 to
500
3. Run "Level resources" with "Day by day", Leveling Order "Standard,
Priority"
Following dates are calculatesd
Id Task Duration Start End
Predec Ressources
1 T1 5 days Mon 26.12.05 Fri 30.12.05 A
2 T2 5 days Mon 26.12.05 Fri 30.12.05 B
3 T3 5 days Mon 09.01.06 Fri 13.01.06 4SS A
4 T4 5 days Mon 02.01.06 Fri 06.01.06 B
Task T3 begins on 09.01.06 and not as expected on 02.01.06.
Andy
i observe some very strange behaviour of the leveling algorithm of the
MS Project 2003 and would appreciate any ideas on how to fix it.
MS Project Info
------------------------
MS Project Professional 11.0.2003.0816.15
Steps to reproduce a bug
------------------------
1. Create new project
2. Create tasks
Id Task Duration Start End
Predec Ressources
1 T1 5 days Mon 26.12.05 Fri 30.12.05 A
2 T2 5 days Mon 26.12.05 Fri 30.12.05 B
3 T3 5 days Mon 26.12.05 Fri 30.12.05 4SS A
4 T4 5 days Mon 26.12.05 Fri 30.12.05 B
3. Set Prio of Task T1 and T2 to 520, Set Prio of Tasks T3 and T4 to
500
3. Run "Level resources" with "Day by day", Leveling Order "Standard,
Priority"
Following dates are calculatesd
Id Task Duration Start End
Predec Ressources
1 T1 5 days Mon 26.12.05 Fri 30.12.05 A
2 T2 5 days Mon 26.12.05 Fri 30.12.05 B
3 T3 5 days Mon 09.01.06 Fri 13.01.06 4SS A
4 T4 5 days Mon 02.01.06 Fri 06.01.06 B
Task T3 begins on 09.01.06 and not as expected on 02.01.06.
Andy