S
Simon
Since Project sometimes seems to have a mind of its own, I would be
grateful if anyone can shed some light on exactly what it is doing in
the following fixed-duration task creation scenario. It seems to
happen on all standalone versions of MSP from 98 upwards and, in all
cases, the software is 'as installed'.
On a new project, create a single Fixed-Duration, non-effort-driven
task with a duration of 32hr and a PSD of 1/8/05. The task is
automatically given a PFD of 4/8/05 which, seems correct. Then use
split to show the 'Resources & Predecessors' form and add a single
resource CFITT with Units=2 and Work =64hr. Pressing OK accepts this
information unchanged (as would expected, from the standard scheduling
equation).
Now create a new task but, instead of initially creating it on the
task sheet, create it via the 'Resources & Predecessors' form. Enter
Task name, Duration (32hr), PSD (1/8/05), Task type (Fixed-Duration),
Resource name (CFITT) Units (2), Work (64hr) and press OK. I would
have expected this to behave in the same way as the first task.
However, although the same PFD (4/8/05) is generated and the Duration
stays the same, Units become 8 and Work becomes 256hr! Although this
still equates to a Duration of 32 hr, why on earth has it ramped the
figures up from 2 and 64hr, respectively?
All enlightenment gratefully received since this has my Project-using
colleagues and myself more than somewhat baffled.
grateful if anyone can shed some light on exactly what it is doing in
the following fixed-duration task creation scenario. It seems to
happen on all standalone versions of MSP from 98 upwards and, in all
cases, the software is 'as installed'.
On a new project, create a single Fixed-Duration, non-effort-driven
task with a duration of 32hr and a PSD of 1/8/05. The task is
automatically given a PFD of 4/8/05 which, seems correct. Then use
split to show the 'Resources & Predecessors' form and add a single
resource CFITT with Units=2 and Work =64hr. Pressing OK accepts this
information unchanged (as would expected, from the standard scheduling
equation).
Now create a new task but, instead of initially creating it on the
task sheet, create it via the 'Resources & Predecessors' form. Enter
Task name, Duration (32hr), PSD (1/8/05), Task type (Fixed-Duration),
Resource name (CFITT) Units (2), Work (64hr) and press OK. I would
have expected this to behave in the same way as the first task.
However, although the same PFD (4/8/05) is generated and the Duration
stays the same, Units become 8 and Work becomes 256hr! Although this
still equates to a Duration of 32 hr, why on earth has it ramped the
figures up from 2 and 64hr, respectively?
All enlightenment gratefully received since this has my Project-using
colleagues and myself more than somewhat baffled.