Hello,
On a user's Gantt Chart, the tracking data (Actual Work) received from PWA
Timesheets, are well displayed in the Task Usage view. For ex. on 20, 21 et
22 of March. But the black progress bar in the Gantt Chart extends on the
next 2 weeks !
Nb : the task type is Fixed units. If I set the task type to Fixed Duration,
the progress bar displays on 3 days as I expected.
Any idea?
Thanka ahead !