I have a proejct that starts on 22nd March and have set Friday as short day
throughout the project starting from April only (friday is a 5 hour day
instead of 7). I would expect project to schedule an 8 hour day for the
first Friday in the project for a task scheduled on that day with one
resource assigned but instead it is putting in 5 hours and then the remaining
3 on the Monday even thought that Friday isn't a short day - help! Also later
on it is then scheduling weird stuff like 7 hours one day and a remaining 1
hour the next instead of 8 hours on one day - I've looked at how the tasks
are linked but can't work it out - default task type is fixed duration.
Thanks, Anita
throughout the project starting from April only (friday is a 5 hour day
instead of 7). I would expect project to schedule an 8 hour day for the
first Friday in the project for a task scheduled on that day with one
resource assigned but instead it is putting in 5 hours and then the remaining
3 on the Monday even thought that Friday isn't a short day - help! Also later
on it is then scheduling weird stuff like 7 hours one day and a remaining 1
hour the next instead of 8 hours on one day - I've looked at how the tasks
are linked but can't work it out - default task type is fixed duration.
Thanks, Anita