R
roadkill
What causes a split to show at the end of a task (i.e. all of the work is
shown in a bar followed by a split, but no bar/work after the split)? This
results in tasks showing 100% work complete but something less % complete.
These tasks use Fixed Duration and, fortunately, I've found that I can
eliminate the split at the end by switching to Fixed Units or Fixed Work and
then back to Fixed Duration. But what causes this weird split (so I may be
able to avoid their creation)?
shown in a bar followed by a split, but no bar/work after the split)? This
results in tasks showing 100% work complete but something less % complete.
These tasks use Fixed Duration and, fortunately, I've found that I can
eliminate the split at the end by switching to Fixed Units or Fixed Work and
then back to Fixed Duration. But what causes this weird split (so I may be
able to avoid their creation)?