T
TraceyH
I added the standard (not customized) 'status' column into Gantt view. 2
related questions.
1) What constitutes a 'late' task? ( I have some tasks that I have updated
actuals today and task still shows late). I have not set a project baseline.
Task is a 'fixed duration' type task.
2) I have a 'placeholder task' that occurs over a 6 month duration (no
resource assigned) that I have set as a milestone. This also show 'late'. How
can I update it (or configure that task differenty) so it never shows up late
related questions.
1) What constitutes a 'late' task? ( I have some tasks that I have updated
actuals today and task still shows late). I have not set a project baseline.
Task is a 'fixed duration' type task.
2) I have a 'placeholder task' that occurs over a 6 month duration (no
resource assigned) that I have set as a milestone. This also show 'late'. How
can I update it (or configure that task differenty) so it never shows up late