A
Al
I have several resources that are showing "red" for overallocated in the
Resource Usage view. The standard calendar and working time show a 40 hour
work week. However, the resources in question only show work allocated to
them in the 18 to 25 hours per week. But they still show as overallocated.
Compounding my concern is that other resources with similar -or less - work
assignments do not show as overallocated.
All resources are 100% to all tasks.
Resource Usage view. The standard calendar and working time show a 40 hour
work week. However, the resources in question only show work allocated to
them in the 18 to 25 hours per week. But they still show as overallocated.
Compounding my concern is that other resources with similar -or less - work
assignments do not show as overallocated.
All resources are 100% to all tasks.