D
Daniel Jameson
Hi,
Our PMO is taking a half-@$$ed approach to implementing MS Project files (MS
Project 2007 SP1). We have at least a dozen projects in progress, each with
its own isolated project file. Most team members are in one or two project
files. However, I'm in most of them, with critical path tasks. The one
real trouble I am having is figuring out what I'm supposed to be working on
this week. As far as I can tell, I have to go into each and every file,
filter the resources column down to my name, and then look at every task
line item to see if the date range includes this week.
Is there a way to get, at least in one file at a time, a report, or
calendar, that says for a specific resource which tasks have a date range
that includes today (or any specific date) and the associated amount of work
hours for that task?
--
Thank you,
Daniel Jameson
SQL Server DBA
Children's Oncology Group
www.childrensoncologygroup.org
Our PMO is taking a half-@$$ed approach to implementing MS Project files (MS
Project 2007 SP1). We have at least a dozen projects in progress, each with
its own isolated project file. Most team members are in one or two project
files. However, I'm in most of them, with critical path tasks. The one
real trouble I am having is figuring out what I'm supposed to be working on
this week. As far as I can tell, I have to go into each and every file,
filter the resources column down to my name, and then look at every task
line item to see if the date range includes this week.
Is there a way to get, at least in one file at a time, a report, or
calendar, that says for a specific resource which tasks have a date range
that includes today (or any specific date) and the associated amount of work
hours for that task?
--
Thank you,
Daniel Jameson
SQL Server DBA
Children's Oncology Group
www.childrensoncologygroup.org