what do the percentages next to resources names indicate in the ga

J

JonnoMo

Hi

Does anyone know what the percentages to the right of resources mean exactly?

"Im also using Project Server"

I have task 100% complete with the allocated time used - not under or over
budget yet they don't say 100% i hav efigures like 44%, 31%, 25% etc.

One resource isnt complete yet and has 2 resources assigned to the task yet
shows 106% - im confussed!

Any ideas????

JMo
 
D

Dale Howard [MVP]

JMo --

The percentage you see to the right of the resource name in the Gantt Chart
view is the Peak Units value. This value represents the largest amount of
either Actual Work or scheduled Work in any time period across the life of
the task assignment. Hope this helps.
 