I am assuming you are doing it within Project and not using Paste in another
application.
The difference is subtle, all I can see on this end is that when you paste
as Text data you create a Start No Earlier Than (SNET) constraint on the
Start date.... as if you had typed it. If you paste as Project Data you do
not create such a constraint... you'll need to try it with different fields
to see if there is anything else of significance. Generally, you will want
to paste as Project Data.
There is another scenario... if you copy a date (say a Start Date) and then
paste special that date to another date column, you are prompted if you want
to paste as text or a link. You can read about linking in the help ....
essentially that is how you create Hammock tasks but I don't want to get off
topic.
--