What happens if team members don't update the Actual Start date?

L

Lisa C

When a project member updates actuals via Project Web Access, what happens if
they don't provide an Actual Start date? Does Project use the Scheduled
Start date?
Should I insist that everyone update the Actual Start?
 
R

Rod Gill

If you enter a % complete, the scheduled start date is used. If you are
entering actual hours on a daily basis, the date of the day with the first
actual work is the actual start date.
 
M

MIP

if you are entering actual hours on a daily basis, does the actual finish
date automatically become the last day the actual work was entered?
 
D

Dale Howard [MVP]

MIP --

It is the last date in which Actual Work is entered and which causes
Remaining Work to be recalculated at 0 hours. Hope this helps.
 