J
jremmc
MOPS 2007 SP2 and tracking method is % work complete
If a task duration is 8 hours and the team member does the work in 8 hours
but not within Start/Finish dates (e.g. task was to start/finish on same day
but actual was 4 hours one day and 4 hours a week later), what is correct way
for team member to update task in Assignment Details page? So that the
duration does not change (e.g. the task duration should not become 35 hours
but the actual finish date should be recorded.) What fields on Assignment
Details page should be changed or should not be touched?
Obviously I am asking because I wreaked havoc on the task. Updating the %
complete to 100% did not change Finish Date, and changing the Finish date
made a mess of duration (the task became 4 days not 8 hours) and trying to
change the Finish Date back changed the Start Date to a week earlier. It just
got worse from there, and I did not find a way to undo from My Tasks once
Saved (though accepting the changes and re-editing the project as PM resolved
mess.)
Thanks,
jremmc
If a task duration is 8 hours and the team member does the work in 8 hours
but not within Start/Finish dates (e.g. task was to start/finish on same day
but actual was 4 hours one day and 4 hours a week later), what is correct way
for team member to update task in Assignment Details page? So that the
duration does not change (e.g. the task duration should not become 35 hours
but the actual finish date should be recorded.) What fields on Assignment
Details page should be changed or should not be touched?
Obviously I am asking because I wreaked havoc on the task. Updating the %
complete to 100% did not change Finish Date, and changing the Finish date
made a mess of duration (the task became 4 days not 8 hours) and trying to
change the Finish Date back changed the Start Date to a week earlier. It just
got worse from there, and I did not find a way to undo from My Tasks once
Saved (though accepting the changes and re-editing the project as PM resolved
mess.)
Thanks,
jremmc