Hi JP,
Project Server 2003 is a Project Tool and Support tasks are not necessarily
handled niclely. By saying that, you can solve this in different ways. Here
are some ways that you can concider:
1. One Poject per department with pre-definded tasks. Create a Template with
the pre-definded tasks and each period (week, month etc) you close this
project and create a new support project. This will allow you to have a
history per period.
2. if the support doesnt require many tasks, create a project called
something like "Support Tasks". Assign the resources as required. ( same
concept then above, but different level, like longer period ( anually ) and
accross the organisation ( not per department).
3. Project Server has the concept of Admin Projects ( which captures all non
project work) Depending on your requirements ( you may only want to capture
actual work for Support) you could use an Admin Project. Please note that
Admin Projects are "special" proejct wich will have some implications ( for
example, if you assign a resource to a task within admin projects, the
availability is not considered).
I hope this will give you some ways to work with