S
slippymississippi
I entered the estimated length of my task as 4 days. This shows up in
the project server database as "19200"
Okay, so 19200 divided by 4 days is 4800. 4800 divided by 8 (hours /
day) is 600. 600 divided by 60 (minutes per hour) is 10.
10?
10 what?
Is it really necessary to track my time in 6 second increments?
the project server database as "19200"
Okay, so 19200 divided by 4 days is 4800. 4800 divided by 8 (hours /
day) is 600. 600 divided by 60 (minutes per hour) is 10.
10?
10 what?
Is it really necessary to track my time in 6 second increments?